1. STRUCTURE
Foundations Single or continuous,
reinforced-concrete bases, minimum characteristic resistance 150
kg/cm2. Continuous foundation pits will be stepped on land with a
gradient. Bearing walls Cemented concrete blocks, 19 cm in width.
Corners and angles connected. Joists and wall connections will be
reinforced with concrete bands (Rk = 175 kg/m2) housed in U-shaped
parts. Horizontal structure Framework of prestressed concrete,
concrete vaults and 4 cm compression layer with steel grid. The roof
joists on the terraces are sloped and formed by wooden beams, boards
and a compression layer of concrete. An adequately ventilated air
chamber is formed between the ground and the first joists. Asphalt
tiles will be placed under the frame and over support bands to
prevent dampness.
2. EXTERIOR WALLS
Exterior walls are formed by block
walls, cemented on both sides, a 4 cm air chamber with heat
insulation (Porespan) and a plastered 7 cm brick wall. Spaces will
be filled with artificial stone. A metre-wide pavement will be laid
around the house, paved with terracotta. No pavement will be laid
when the difference in the level between the house and the ground is
more than 1 m. Exterior balcony rails will be formed by artificial
stone balusters. The sloping root will be formed by walls and board,
with a compression layer and arab roof tiles. The eaves will be
formed by wooden brackets or two rings of solid brick. If the walls
are to be higher than 1,30 m, a new frame will be used with an
adequate slope. In all cases, the roof will have adequate
ventilation. In the case of flat roofs, the slopes will be formed
with light materials over a heat insulation layer, covered by
asphalt tiles and terracotta.
3. INTERIOR WALLS
The interior distribution will be
made with plastered 7 cm ceramic brick walls, with plaster-mold
finish around the perimeter. A prefabricated fireplace will be
installed in the living room. The fireplace is made of refractory
firebricks and will be decorated with natural stone and a wooden
mantelpiece.
4. FLOORING AND TILING
Floors will be covered in
first-quality ceramic tiles to be chosen from the standard samples
on show at our offices. Terracotta will be used for outside paving.
Baseboards will be of the same material as the flooring. Walls will
be tiled up to the ceiling with materials chosen from our samples.
When there is a staircase inside the house, the steps will be
covered using the same materials as for the floors, with wooden
springboards and fronts. The stair railing will be made of wood with
vertical turned rails and handrail.
5. KITCHEN FURNITURE
Solid wood doors, provencale style,
as per samples at our office, with molded finish on high cupboards.
All kitchens will have a set of drawers, mid-cupboard shelves and a
space for a dish-washer and a washing machine. The work-top will be
pink "porch" granite with a double, white Sylacril sink
unit. Electric vitroceramic hob. Electric oven. An extractor
hood will be installed.
6. INTERIOR CARPENTRY
Interior door leaves will be solid
wood, with mobila wood veneer and panels, as per samples. Reinforced
main door with security lock and three anchorage points. Wardrobe
doors will be the same as interior doors. The interior of the
wardrobes will be covered in Melamine, with a set of drawers and
clothes rail.
7. EXTERIOR CARPENTRY
White lacquered aluminuim, European
profile, with laminated safety glass. PVC roller blinds in the
bedrooms.
8. PAINTWORK The rustic-finish
cement exterior will be painted with plastic paint in the colours
chosen by the client. Interior paintwork in flattened plastic Artex.
Woodwork will be given a coat of primer and varnished in its natural
colour. Locks will be given two coats of anti-rust paint.
9. PLUMBING INSTALLATION AND
BATHROOM FITTINGS
The interior installation will be
protected copper piping. Hot water will be supplied from a 100 1
electric water heater. Mixer taps, mark "GROHE", model "EURODUR" or
similar. "ROCA" bathroom fittings, model "DAMA ", white or similar.
Hydro-massage bath in main bathroom. Three equidistant water
connections for irrigation installed outside the house.
10. ELECTRICAL INSTALLATION
The electrical installation will
comply with existing regulations, with a high level of
electrification (8.000 W). Mechanisms will be model "IBIZA" or
similar and all power points will be earthed. The distribution of
light points, sockets, etc. will be according to Project design. A T
V and M.F aerial will be installed with two connections in the house
(in the living room and main bedroom). A telephone line will be
installed from the plot boundary, with two connections inside the
house. Exterior light points and power points will be installed on
the terrace, with a further four points for lighting the outside of
the house. |